2023 Capital Schedule
- Master planning for Primrose Farm Park, Hickory Knolls Discovery Center and Otter Cove Aquatic Park splash park
- District-wide Door Access System
- Equipment replacements for the Park, Recreation and Golf Departments
- Asphalt upgrades to Timber Trails Park, Pottawatomie Park and along the Fox River Trail
- Pavement and sealcoating repairs at Cambridge Park, Fox Chase Park, Pottawatomie Park, James O. Breen Community Park and Mt. St. Mary Park
Playground renovations to be completed in 2023
Red Gate Park
Kehoe Park
Baker Field Park
Delnor Woods Park
Fall 2022 – Community Input Survey Completed
Winter 2022 – Final Construction Documents developed with resident selected playground equipment
February 2023 – Project issued for Public Bid
March 2023 – Board consideration of lowest responsible bidder, contracts issued and equipment ordered (10-12 weeks until delivery)
July 2023 – Anticipated playground equipment arrives, construction begins
Timber Trails Park
Fall 2022 – Community Input Survey Completed
Winter 2022 – Final Construction Documents developed with resident selected playground equipment
February 2023 – Project issued for Public Bid
March 2023 – Board consideration of lowest responsible bidder, contracts issued and equipment ordered (10-12 weeks until delivery)
July 2023 – Anticipated playground equipment arrives, construction begins